Task description

Expansion of capacities at the Leinfelden site to realize Europe-wide supply

Industry Consumer/investment goods

Project location Stuttgart

Project duration 10 – 12 months

Investment volume ca. 2.5 Mio. €

Area Hochregallager mit 2.300 m², 8 Gassen

Capacity 6.500 Palettenstellplätze

Industry Consumer/investment goods

Project location Stuttgart

Project duration 10 – 12 months

Investment volume ca. 2.5 Mio. €

Area Hochregallager mit 2.300 m², 8 Gassen

Capacity 6.500 Palettenstellplätze