Weltbild: planning and realization of shuttle warehouse

Verlagsgruppe Weltbild GmbH

Company

Services from IWL

  • Evaluation and selection of the concept
  • Preparation of tender documents and bid comparison
  • Support during the realization phase
  • Support during test and commissioning

Customer benefit

  • Increase of the delivery speed
  • Improvement of delivery readiness and quality

Task description

  • Increasing the effectiveness and efficiency of the multi-channel logistics center in Augsburg
  • Development of multi-channel strategy

Project video
YouTube

Mit dem Laden des Videos akzeptieren Sie die Datenschutzerklärung von YouTube.
Mehr erfahren

Video laden

Industry Media

Project location Augsburg

Project duration 2011 - 2013

Special features Cross belt sorter as central distributor connects the rack system with a total of 12 high-performance workstations

Capacity Behälterlager: 43.000 Stellplätze in 6 Gassen und 2 Ebenen

Services picking of 7.000 parts / hour

Industry Media

Project location Augsburg

Project duration 2011 - 2013

Special features Cross belt sorter as central distributor connects the rack system with a total of 12 high-performance workstations

Capacity Behälterlager: 43.000 Stellplätze in 6 Gassen und 2 Ebenen

Service picking of 7.000 parts / hour

IWL AG | We optimize processes